Digtown Construction Update
May 15, 2012 - Construction is moving north on 2nd Avenue. 2nd Avenue is closed on the north and south side of Moulton Street for sidewalk construction.
This Construction Schedule is subject to change due to the weather.
- 4/9 to 4/13 Close 2nd Avenue @ Grant St.
- 4/10 to 4/14 Close 2nd Ave.from center of block between Grant & Johnston St. thru Grant St.intersection.
- 4/13 Start @ Southwest corner of Johnston St.
- 4/16 to 4/20 Close Johnston St. West side @ 2nd Avenue
- 4/18 Start @ Northwest corner of Johnston St. intersection
- 4/23 to 4/29 Close 2nd Ave. @ Johnston St.
- 4/25 Start @ center of block between Johnston & Moulton St.
- 4/30 to 5/4 Close 2nd Ave. @ crosswalk between Johnston & Moulton Street
- 5/1 start Southwest corner @ Moulton St.
- 5/2 to 5/4 Close 2nd Avenue @ Moulton St., South side.
- 5/3 Start Northeast corner @ Moulton Street
- 5/7 to 5/11 Close North side or 2nd Ave. @ Moulton St.
- 5/9 Continue North from Moulton St.
- 5/21 to 5/25 Close alley across from Princess
- 5/21 Start @ North corner of alley & contine North.
- 6/6 to 6/11 Close center lane @ Lee St.
- 6/12 to 6/18 Close West lane @ Lee St.
- -6/22 Projected completion of project.